Modelling Procurement Deliveries for Earned Value Management Using Level-of-Effort Logic

##article.authors##

  • Antoine Scaperrotta Independent Searcher

DOI:

https://doi.org/10.31224/5811

Keywords:

Earned Value Management (EVM), Procurement Delivery Modelling, Level of Effort (LOE), Programme Dynamic Delivery Span, Programme Procurement Visibility, Logic-Driven Procurement Window, Last Delivery Milestone

Abstract

Procurement remains one of the least mature elements in most Earned Value Management (EVM) systems. Conventional CPM schedules typically represent material deliveries as single-point events or fixed-lag activities, which conceal delivery uncertainty and weaken compliance with DCMA schedule-quality criteria [1]. This paper introduces a Level-of-Effort (LOE) Delivery Modelling Pattern [2] that enables planners to represent procurement deliveries as a dynamic time span between the first dispatch and the final required receipt. The LOE provides schedule visibility through standard SS/FF logic, while earned value and cash-flow recognition occur only at discrete receipt milestones. This event-driven approach ensures compliance with AACE RP 79R-13 [3], 88R-15 [4], and EIA-748 [5], aligns BCWP, ACWP, and actual payment timing, and produces S-curves whose cost and liquidity profiles better reflect project reality. A practical EPC case study demonstrates improved schedule-logic quality, financial traceability, and audit readiness, establishing the LOE delivery pattern as a repeatable, standards-aligned solution for integrating procurement, EVM, and cash-flow control.

Downloads

Download data is not yet available.

Downloads

Posted

2025-11-17