Modelling Procurement Deliveries for Earned Value Management Using Level-of-Effort Logic
DOI:
https://doi.org/10.31224/5811Keywords:
Earned Value Management (EVM), Procurement Delivery Modelling, Level of Effort (LOE), Programme Dynamic Delivery Span, Programme Procurement Visibility, Logic-Driven Procurement Window, Last Delivery MilestoneAbstract
Procurement remains one of the least mature elements in most Earned Value Management (EVM) systems. Conventional CPM schedules typically represent material deliveries as single-point events or fixed-lag activities, which conceal delivery uncertainty and weaken compliance with DCMA schedule-quality criteria [1]. This paper introduces a Level-of-Effort (LOE) Delivery Modelling Pattern [2] that enables planners to represent procurement deliveries as a dynamic time span between the first dispatch and the final required receipt. The LOE provides schedule visibility through standard SS/FF logic, while earned value and cash-flow recognition occur only at discrete receipt milestones. This event-driven approach ensures compliance with AACE RP 79R-13 [3], 88R-15 [4], and EIA-748 [5], aligns BCWP, ACWP, and actual payment timing, and produces S-curves whose cost and liquidity profiles better reflect project reality. A practical EPC case study demonstrates improved schedule-logic quality, financial traceability, and audit readiness, establishing the LOE delivery pattern as a repeatable, standards-aligned solution for integrating procurement, EVM, and cash-flow control.
Downloads
Downloads
Posted
License
Copyright (c) 2025 Antoine Scaperrotta

This work is licensed under a Creative Commons Attribution 4.0 International License.